|
We believe their are two preferred options for
the walk/cycleway, each requires a small add-on to the existing clip-on
deck in order to provide a walkway on the outer edge of the Eastern deck
and a cycleway on the outer edge of the Western deck.
The two options are:
1) A 590mm add-on. See page
3 of these drawings by Beca.
2) A 340 mm add-on, as
shown here.
Both options allow for very
good connections, particularly on the North Shore side.
We
are mindful of the work completed last year by Beca's which was based on
the options at either end of the spectrum of 'No widening' and 'Maximum
widening'. Both options were
ultimately rejected due to the first being too narrow and the second too
expensive (Beca's estimate in June 07: $30 to 40 million).
We believe that Maunsells were
engaged to find an optimised solution for the walk/cycleway - likely to
somewhere between the two extremes of 'No
widening' and 'Maximum widening', so we have real concern that
Maunsells has repeated the rejected options as their preferred.
We understand that that the IE has subsequently requested that Maunsell
includes the “600mm add-on” as shown in drawing 603 (on page 3
attached) as a preferred option. We strongly support the IE’s
initiative in this request as we believe that this ‘middle option’
is superior for the following reasons:
- Lower
costs:
Due to less materials and lower weight (and consequently less
strengthening), such an option will be significantly cheaper than
the 'maximum add-on' . It also appears that this option would
only require 4 due trough splices to be strengthened (due to changed
wheel track alignment), whereas the 'no add-on' and 'maximum add-on'
will require 6 trough splices to be strengthened.
- Better
Access:
Any widening options of more than 600 mm are likely to require the
use of elevators at the northern end because it is not likely the
necessary airspace can be obtained from the private residences on
Northcote Point. Elevators are not only very expensive to
install, but they also cause delays for commuters, have extra
maintenance costs and reduce the connectivity options for the
walk/cycle way. An add-on of 590mm can be accommodated within
the available northern approach viaduct because it is 1.06 m wider
than the clip-ons narrowest width of 9.757m.(see diagrams A and C
from Drawing SK41 of Beca's report: AHB Cycleway - Feasibility Study
Stage 1, July 06)
- Adequate
lane widths: With revised hand rails (to meet the new
standards) a walk/cycleway width could be 2.6m, whilst traffic lane
widths could be 3.4m for lane 1, (which is the de facto bus lane and
the would accommodate the wider buses planned by Ritchie's) and 3.2m
for Lane 2, with shoulder widths of 250mm.
Given their ultimate rejection
last year, we have requested the IE to that Maunsell removes both the
'No add-on' and 'Maximum add-on' options from their preferred options
list.
We recommend that the option
of the 340mm add-on is included in the preferred options, as we believe that the
340mm add-on could potentially be even
more advantageous than the “600 add-on” given that it
provides adequate lane widths, does not require elevators on the
Northcote Point and is likely to be less expensive due to the reduced
materials and stress loadings of such a 340 mm add-on.
|